Rates
On this page
What are rates?
Rates set how much an hour (or a day) of each person costs and how much is charged for travel. With them, work reports calculate the amount for each technician's hours, and the work report export comes out with those prices.
Open Menu › Commercial › Rates, next to Articles. The page is available with Management or Full access; the Travel section can only be seen and changed with Full Access, because it is an organization-wide setting. If you use it often, add Rates to your shortcuts in My account › Navigation.
The page has three sections: Price per person, Labor rates and Travel.
Price per person
It lists every active person in the organization with the rate that prices their hours and the amount (for example €45.00/h or €280.00/day). In the header, a counter such as 5/6 with a price shows how many people have a price; it is shown in orange if anyone is missing one. People without a rate appear as No price.
To change a person's rate, choose another one in the dropdown on their row. enrutar asks for confirmation (Move <person> to <rate>?), showing the previous and the new price, and warns that Existing work reports keep their price · Only new ones change. The Change to <price> button saves the change.
If a person needs a price just for them, choose Own price for <name>… in their dropdown: a new rate opens that already applies to that person.
Labor rates
Here are the labor rates, with who they apply to (Everyone, the number of people or Unassigned) and their price. Click a rate to edit it or New rate to create another. Each rate has:
- Name: for example
TechnicianorHelper. - Price: per hour (
Per hour) or per day (Per day). - Applies to:
EveryoneorSpecific people. WithSpecific peopleyou choose the people from a list; if you don't choose anyone, the rate staysUnassignedand is not used on work reports.
Rules:
- Only one rate can apply to
Everyone. - Each person has at most one rate of their own. In the list, people who already have a price in another rate appear locked (
Already priced in): remove them from that rate first or change them fromPrice per person. - A person's own rate takes priority over the
Everyonerate. - A daily rate charges one day for each different day the person worked on the work report.
- If the rate has already been used on a work report, it cannot switch from hourly to daily or the other way round: create a new rate.
When a change affects what work reports will charge, the dialog reminds you with Existing work reports keep their price · Only new ones change.
To stop using a rate, open it and click Archive. enrutar asks for confirmation; the people it covered move to the Everyone rate, or are left without a price if there is none. Archived rates are shown with Archived · N and recovered with Restore.
Travel
Charge travel decides what happens to the driving time from time entries when a work report is prepared:
Don't charge: driving does not go into the work report. Time entry reports still show it.As work(default option): driving is charged as working hours, at each technician's rate.Per visit: the work report adds a travel line for each appointment with driving, for exampleTravel (28/10). If several technicians go to the same appointment, they share a single line. Enter the amount inPrice per visit.Per hour: driving hours are charged atPrice per hourinstead of at each technician's rate.
Below the option, an example with two technicians shows how many lines each mode generates and their amount. With Per visit or Per hour, until you enter a price, driving is charged as working hours (No price yet: billed as hours of work). When you change a price already saved, existing work reports keep theirs.
Rounding of driving and working time is configured separately, in Settings › Calendar › Work reports. See Work Reports.
Prices fixed on work reports
Each work report fixes the price of its hours and its travel when it is created, with the rates in force at that moment. The work report shows this with Prices of <date>. Changing a rate or moving a person to another rate never changes work reports already created, signed or not: only new ones use the new price.
The only exception is the hours of a person who had no rate when the work report was created: they take the current rate until the work report is signed. Meanwhile, the work report shows Current rate and the form shows Locked when signed.
Rates and articles
Rates do not appear in Articles and are not created from there: they are managed only on this page. This way, tidying up the catalogue does not change the price of work reports by mistake.
Rates are not shown to users with Restricted access: on work reports they see the hours without their price.
Related entities